Join a project email list
We are committed to keeping neighbors and interested parties informed about our pipeline projects. Click the following streets to sign up for a project-specific email list for regular news and updates:
Questions? Contact the pipelines project team at pipeline@eweb.org.
EWEB is working on several pipeline projects to enhance the reliability and seismic resiliency of drinking water service for Eugene residents. The work is part of a multi-year plan to upgrade aging infrastructure and build new water facilities designed to withstand a large earthquake or other natural disaster.
EWEB is committed to being a good neighbor during construction by completing projects as safely and efficiently as possible, but construction may cause traffic disruptions or other inconveniences. Whenever possible, work will be coordinated to reduce the impacts on close by neighbors, businesses, and travelers.
Important safety reminders:
- Avoid active work zones if possible.
- When you need enter the work zone, please wait for the contractor or EWEB staff to escort you safely through. This may take a few minutes but will ensure you pass though the work area safely.
- Make sure to check your surroundings, including overhead.
- When heavy equipment is in use, make eye contact with the operator and wait for them to acknowledge you before entering the work zone.
- Remember that construction equipment can move suddenly and quickly.
- Don't linger. Get through quickly and watch your step.
Learn more about our pipeline projects: Chambers St. | Dillard Dr. | Bethel Dr. | Myaok Dr. | Other Upcoming Projects | Completed Projects | E. 24th Ave.
Chambers St. From 13th Ave. to Amazon Creek
EWEB will be replacing water distribution mains and services on Chambers St. from W 13th Ave. to Amazon Creek. This project will upgrade pipes that were originally installed in 1948 with modern ductile iron pipes to provide greater reliability.
Estimated Timeframe
July to September 2026
Traffic Impacts
The Chambers St. southbound lane will be closed during construction hours and will reopen each evening. Traffic will be controlled with 4-way flagging at the intersection of W. 13th Ave., and a detour route on Polk St. will be provided during road closures. The northbound lane will remain open. See the on-site reader board for any changes.
Neighbors will still be able to access their street and homes. If crews need to shut your water off or block your driveway access to complete work, they will notify neighbors and provide additional information directly ahead of time.
For everyone’s safety, please observe all posted traffic controls, parking restrictions, and detours. Slow for crews to ensure everyone’s safety.
Neighborhood Impacts
Construction activity will create noise, vibration, dust, and may disrupt normal neighborhood activity. Work will typically begin at 7:00 a.m. and conclude by 5:00 p.m., Monday through Thursday.
Repaving Coordination with the City of Eugene
The Chambers pipeline project is in coordination with the City of Eugene Pavement Project to address pavement condition. New street trees will be planted and some traffic signals will be modified. The partnership reduces the costs for both the City of Eugene and EWEB and minimizes traffic impacts for the community.
Join the Chambers St. Email List
Dillard Rd. from Hilyard St. to W. Amazon Dr.
EWEB will be replacing water distribution mains and services on Dillard Rd. from Hilyard St. to West Amazon Dr. This project will upgrade pipes originally constructed in the 1960's with larger diameter pipes to increase flow for fire protection and provide greater reliability.
Estimated Timeframe
September to December 2026
Traffic Impacts
Crews will maintain local access for residents during traffic delays and road closures to ensure access to homes. Additional direction by crews may be necessary at times. If crews need to shut your water off or block your driveway access to complete work, they will notify neighbors and provide additional information directly ahead of time.
For everyone’s safety, please observe all posted traffic controls, parking restrictions, and detours. Slow down for crews to ensure everyone’s safety.
Neighborhood Impacts
Construction activity will create noise, vibration, dust, and may disrupt normal neighborhood activity. Work will typically begin at 7:00 a.m. and conclude by 5:00 p.m., Monday through Thursday.
Bethel Dr. from Roosevelt Blvd. to Allane Ave.
EWEB will be replacing water distribution mains and services on Bethel Dr. from Roosevelt Blvd. to Allane Ave. This project will upgrade 70-year-old cement pipes with larger diameter pipes to increase flow for fire protection and provide greater reliability.
Estimated Timeframe
May to August 2026
Traffic Impacts
EWEB crews will keep one lane open with flaggers to direct traffic. Neighbors will still be able to access their street and homes. If crews need to shut your water off or block your driveway access to complete work, they will notify neighbors and provide additional information directly ahead of time.
For everyone’s safety, please observe all posted traffic controls, parking restrictions, and detours. Slow for crews to ensure everyone’s safety.
Neighborhood Impacts
Construction activity will create noise, vibration, dust, and may disrupt normal neighborhood activity. Work will typically begin at 8:00 a.m. and conclude by 5:00 p.m., Monday through Thursday.
Repaving Coordination with the City of Eugene
The Bethel Dr. pipeline project is in coordination with the City of Eugene repaving project to address pavement age and traffic loading. Lighting enhancements and new street trees are also planned as part of this project. The partnership reduces the costs for both the City of Eugene and EWEB and minimizes traffic impacts for the community.
Myoak Dr. from River Rd. to Myoak Drive Cul-De-Sac
EWEB will be replacing water distribution mains and services on Myaok Dr. from River Rd to Myoak Drive Cul-De-Sac. This project will upgrade the current pipes larger diameter pipes to increase flow for fire protection and provide greater reliability. Additionally, fire hydrants will be replaced or added and EWEB will repave the street after the main replacement project is complete.
Estimated Timeframe
May to August 2026
Traffic Impacts
Contractor crews will maintain local access for residents during traffic delays and road closures to ensure access to homes. Additional direction by crews may be necessary at times. If crews need to shut your water off or block your driveway access to complete work, they will notify neighbors and provide additional information directly ahead of time.
Neighborhood Impacts
Construction activity will create noise, vibration, dust, and may disrupt normal neighborhood activity. Work will typically begin at 7:00 a.m. and conclude by 5:00 p.m., Monday through Friday.
Other Upcoming Projects
23rd Ave. from Emerald St. To Alder St.
EWEB will be installing a 42-inch transmission pipe on 23rd Ave. to improve hydraulics of water between water storage tanks at College Hill and East 40th and EWEB’s water distributions system. This project will improve water quality, stabilize system pressures in the area, improve the efficiency of the overall base level system operations, and complete improvements to a vital section of EWEB’s resilient spine.
To minimize future construction costs and neighborhood impacts, this project will also include concurrently upgrading distribution pipeline, installing new services, and new fire hydrants along the pipeline route. The new distribution pipes will increase flow for fire protection and provide reliability for years to come.
The transmission work is tentatively scheduled for late 2026. Installing the transmission pipe will require an open trench and will take multiple months to complete the work. Neighbors will be notified before construction work begins with what to expect and specific timelines. For now, consider joining the 23rd Ave. Email List to stay up-to-date with construction work in this neighborhood.
Other Utility Work Advisories
EWEB is constantly making community investments to prepare, replace and maintain the water system. You may see EWEB construction activity throughout the city. If crews need to shut your water off or block your driveway access to complete work, they will notify you directly ahead of time.
Completed Projects
Hilyard Pipeline Project
The construction work at Hilyard Street and East 33rd Ave was completed in April 2025, marking the end of a multi-year project. Water now flows from EWEB’s Hayden Bridge Water Filtration Plant to the new water storage tanks through the Hilyard water transmission pipeline, and ultimately to homes and businesses. The completed pipeline adds redundancy and resiliency to Eugene’s water system and capacity for firefighting protection. During the project, EWEB also provided electric and water services to Nightingale Hosted Shelters and saved native Camas Bulbs from the construction site.
E. 24th Ave. from Miami Ln. to Agate St.
EWEB upgraded pipes that were originally constructed in 1926. In addition to addressing this aging underground infrastructure, EWEB made additional upgrades to have more control over the flow of water and ensured our system is up to our 2026 standards. Here’s how the project went by the numbers: '

- 2735 ft of distribution mains were replaced with larger diameter pipes. Larger pipes will provide increased flow for fire protection and ensure you have water during high-use times.
- 10 valves were added for EWEB to better control the flow of water. Added valves will reduce water outages when EWEB needs to maintain or fix a particular section of pipe.
- 2 fire hydrants were replaced or added. Upgraded fire hydrants will provide greater fire protection.
Project construction began in October 2025 and was completed in March 2026. There were no reported traffic incidents during this project. Thank you for slowing down and protecting our crews!
Repaving Coordination with the City of Eugene
The 24th Ave. pipeline project is in coordination with the City of Eugene repaving project to address pavement conditions and widen bike lanes. The partnership reduces the costs for both the City of Eugene and EWEB and minimizes traffic impacts for the community. By having EWEB replace the pipelines and make upgrades first, there is a greater likelihood that EWEB will not need to open up the freshly paved street in the near future. Read detailed project updates, information about bike lanes, and sign up for updates on the City of Eugene website.
Email Updates
We are committed to keeping our neighbors informed about this project. Click here to sign up for our E. 24th Ave. project email list or review the previously sent emails below.
April 23, 2026: E. 24th Ave. Pipeline Replacement: EWEB Work Complete
February 2, 2026: E. 24th Ave. Pipeline Replacement: Construction Update
September 30, 2025: E. 24th Ave. Pipeline Replacement: Upcoming Construction Work
Join the 23rd and 24th Ave. Email ListMore Information on Eugene's Water Reliability Projects
We're making investments to prepare, replace and maintain our community's water system.
Access to clean water is vital to our community. That is why we work hard to deliver water that meets or exceeds all state and federal health standards.
EWEB is updating its long-range Water System Master Plan (WSMP) to ensure our community has safe and reliable water for the future. This plan provides guidance for important upgrades over the next 20 years to prepare, replace and maintain the infrastructure that makes up our water system.
